The Matix timeline:
viable progress built to scale.

We are committed to growth.

Mar 25
Urea production touches 1.47 MT against plate capacity of 1.27 MTPA
Jan 25
Floating solar power plant installed contributing 5% to the total energy requirement
Dec24
Dec 24
Receives ‘Best production performance of an operating fertiliser unit for nitrogen for the year 2023-24’ from FAI
Nov 24
Receives ‘CSR Impact Award’ for Project Dhadkan at the CSR Connect Summit
Mar 24
Mar 24
Becomes largest single train urea producer at 1.5 MTPA in FY 2023-24
Feb24
Feb 24
Urea production surpasses annual capacity of 1.27 MTPA in 10 months and 5 days
Jul 23
Jul 23
Market presence grows from five states to nine states
Jan 23
Mini-science Centres established
Dec 22
Project Dhadkan and Project Shakti commence
Oct 22
Oct 22
  • Highest monthly capacity of urea produced (111% capacity utilisation)
  • Product portfolio increases to 9 products
Jul 22
Jul 22
Highest daily capacity of ammonia produced (112.3% capacity utilisation)
May 22
May 22
Trading business commences
Nov 21
Nov 21
100% production achieved
Oct 21
Oct 21
Production stabilised at 80%
Sep 21
Sep 21
Trial production commences
Aug 21
Aug 21
RLNG supply from GAIL commences